References

Alterna has started to co-invest in Natural Gas fired co-generation and combined cycle plants in 2008 which are listed below, and acts as Conceptual Design Engineers, Developer, EPC Owner Engineers and Operators.

Falez Elektrik Üretimi A.Ş.

Antalya OSB co-generation plant, 12 MW installed power , in operation since 2009. Extension to 48 MW in progress.

Beypiliç A.Ş.

Co-generation plant, Bolu 8 MW installed power, in operation since May 2012

Hatipoğlu Elektrik Üretimi A.Ş.

CCPP (combined cycle power plant) Eskişehir 118 MW installed power, under construction, planned operation September 2015

TUGEN Niğde Elektrik Üretim A.Ş.

CCPP, 190 MW installed power, land secured, engineering completed, applied for licencing , planned operation end of 2016

TUGEN Gerede Elektrik Üretim A.Ş

CCPP, 190 MW installed power, land secured, engineering in progress, planned operation end of 2017

TUGEN Sungurlu Elektrik Üretim A.Ş

CCPP, 235 MW installed power, land secured, engineering in progress, planned operation end of 2016

TUGEN Kütahya Elektrik Üretim A.Ş

CCPP, 235 MW installed power, land secured, engineering in progress, planned operation end of 2017

TUGEN Yozgat Elektrik Üretim A.Ş

CCPP, 190 MW installed power, land secured, engineering in progress, planned operation end of 2018